Updated
What running a 300–500 m² house costs.
Over thirty years a 300–500 m² house costs PLN 4.8 to 7.8 million, counting construction, maintenance, repairs, energy and cleaning together. That works out at PLN 450–600 per m² per year, and the figure is surprisingly stable regardless of house size.
We calculated this on twenty houses and apartments from nineteen of our projects, because in a budget conversation the client usually hears one number, the cost of building, and then pays roughly the same again over the next thirty years. The whole model, including how sensitive it is to the assumptions and the cost of a metre of circulation house by house, is set out in the study of the thirty-year cost.
What the bill consists of
Four items, at 2026 prices, excluding the plot and fit-out:
- Construction: 50 to 54 per cent. We assumed PLN 8,000 per m² turnkey, against a market of 6,000–9,000 and up to 10,000 at a higher standard.
- Cleaning: 26 to 31 per cent. Three hours per 100 m² weekly at PLN 110 an hour.
- Maintenance and repairs: 15 to 16 per cent. One per cent of the value of the house per year, the lower end of the 1–4 per cent rule used in home maintenance guides.
- Energy: 3 to 4 per cent. Twenty kWh per m² per year at PLN 1.13, a heat-pump scenario.
These rates are the assumptions of the model in the thirty-year cost study, where we give their sources: 2026 construction costs from Ongeo, Murator and Freenance, the 1–4 per cent a year rule from the University of Minnesota Extension, the price of electricity on the G11 tariff from January 2026 from Murator, and cleaning rates from 2026 price lists for Łódź. The floor areas come from our own designs.
Cleaning costs several times more than electricity
This result surprised us. Over thirty years cleaning costs five to ten times more than all the energy, and it is the second item on the bill right after construction.
A 400 m² house needs twelve hours of cleaning a week. That is a half-time job, every week, for thirty years, or roughly PLN 2 million. All the energy in the same house is about PLN 300,000.
Cleaning is also the only item that grows in direct proportion to floor area, with no economy of scale at all. Every hundred square metres means roughly a hundred and fifty hours a year.
Not every square metre costs the same
| Type of space | Cost per m² over 30 years |
|---|---|
| Room, heated and cleaned | PLN 14,400–18,100 |
| Garage, unheated and uncleaned | PLN 5,200 |
| Terrace | PLN 1,900 |
A square metre of garage is about three times cheaper than a square metre of room, and a terrace about eight times. Above 300 m² a Polish VAT threshold adds roughly PLN 900 per m².
Circulation: the metre nobody orders
A corridor costs exactly as much over thirty years as a room, because it is heated and cleaned the same way. Circulation with halls typically takes 10 to 24 per cent of a house's floor area, which is PLN 0.37 to 1.78 million.
Two numbers are worth keeping in mind at the first sketches. Cutting ten square metres of circulation saves roughly PLN 145,000–180,000 over thirty years. One percentage point in a 270 m² house, just under three square metres, is PLN 40,000–50,000.
What the model excludes
The plot, fit-out, garden, insurance and property tax. There is no inflation and no cost of capital. The cleaning rate matters a great deal: at PLN 70 an hour instead of 110 that item shrinks by a third.
Dates, limits and parameters reflect the law as it stood when the text was last updated. This is not legal advice, nor a design assessment of any particular plot. What you may build is decided by the local plan or the planning decision for your own plot. We are happy to read it.
We will check what fits
on your plot.
Other questions
How much does designing a 400–500 m² house cost How long designing a residence takes: stage by stage Detailed design: what it should contain Services in a 500 m² house: heat pump and ventilation How much building a 500 m² premium house costs Checking a plot in Poland before you buy it Poland's general zoning plan: what it changes for your plot Catalogue or bespoke house design A house in architectural concrete: what to know Design supervision: what the architect does on site Car showroom design: brand standards Building permit in Poland: how long it takes Choosing an architect: portfolio, contract, fee Low-energy or passive: what pays on a 500 m² house How long building a 500 m² house takes How much storage a premium house needs How to orient a house to the sun Mechanical ventilation or an open window A house on a narrow plot: what fits Single storey or two storeys: which pays off A double-height living space: what you gain and lose How many houses fit on a plot A house for two generations