Part 01 ·
Building is half the bill.
The other half is cleaning,
repairs and electricity.
At the table, money means one number: what it costs to build. We worked out what happens to that sum over the following thirty years, and it turns out that building is about half the bill. The other half is made up of three items rarely discussed at design stage.
This is the first part of a series in which we open up our own plan study. The material comes from an analysis of twenty houses and apartments designed by the practice, ranging from 160 to 729 m². This part draws on the chapters about life-cycle cost and about the water balance.
What exactly we are counting
The model covers four items and excludes the plot. All rates are from 2026, with no inflation and no cost of money over time. We assume the house stands for thirty years and is normally used by a family throughout.
| Item | Rate adopted | Source |
|---|---|---|
| Construction | PLN 8,000/m² turnkey | 2026 market: PLN 6,000–9,000/m², up to 10,000 at a higher standard |
| Maintenance and repairs | 1% of the value of the house per year | a rule from personal finance; for older houses 1–4% is assumed |
| Energy | 20 kWh/m² a year at PLN 1.13 | a heat-pump scenario, G11 electricity tariff from January 2026 |
| Cleaning | 3 h per 100 m² weekly, PLN 110/h | market rate PLN 70–150/h; the charts use the middle value |
The model excludes the plot, the fittings, the garden, insurance and property tax.
For three sizes of house from our base it works out like this.
The bar shows the upper value of the range. Per square metre it comes out much the same in every case: PLN 450–600 per m² per year.
The four items on the bill
What is most striking is that the proportions barely change. Whether the house is 240 or 730 square metres, the bill divides the same way.
construction cleaning maintenance and repairs energy
Ranges from the study: construction 50–54%, cleaning 26–31%, maintenance and repairs 15–16%, energy 3–4%.
It is clearer still when, instead of a single bar, you draw how the bill accumulates year by year. Construction sits entirely at the start; the rest adds up every twelve months and after thirty years very nearly catches it.
construction cleaning maintenance and repairs energy
year 010 years20 years30 years
Vertical axis from zero to PLN 4.5 m. Rates as in the table above. The result, PLN 4.35 m, falls inside the range the study gives for houses of 240–270 m²: PLN 3.3–4.5 m.
Cleaning costs several times more than electricity
This is the result that surprised us. Over thirty years, cleaning costs five to ten times more than energy. It is the second item on the bill, right after construction, and the only one that rises in direct proportion to floor area, with no economy of scale at all.
At three hours per hundred square metres a week, a house of 400 m² needs twelve hours of work a week. That is half a job, every week, for thirty years. At PLN 110 an hour it comes to about two million złoty. For comparison, all the energy in the same house is about three hundred thousand.
The practical conclusion is uncomfortable for an architect: every extra square metre that cannot be justified by a function is bought twice. Once when it is built, and again every week for the next thirty years.
What a square metre costs, depending on what it is
Not every square metre costs the same. A heated and cleaned metre is one thing, a metre of garage is something else entirely, and a metre of terrace is practically free compared with either.
For the garage a build cost of PLN 4,000/m² is assumed, for the terrace PLN 1,500/m². In a house over 300 m² a further PLN 900 of higher VAT falls on each metre of room.
A metre of garage is about three times cheaper than a metre of room, and a metre of terrace about eight times. That changes how it is worth talking about the brief. “Do we need a bigger garage” and “do we need a bigger living room” are questions about entirely different money, even though on a plan they look much the same.
The terraces in our houses run from 25 to 135 per cent of the internal living area. In two houses the terrace is larger than the living room, kitchen and dining room together. And it costs about an eighth of what that area costs indoors.
Circulation: a square metre that costs like a room
A corridor is rarely on the wish list, yet over thirty years it costs exactly as much as a room, because it is heated and cleaned in the same way.
For comparison, a two-car garage of about 40 m² costs around PLN 0.2 m over thirty years.
Two numbers come out of the model that are worth having in mind at the first sketches. Taking away ten square metres of circulation is about PLN 145,000–180,000 less over thirty years. One percentage point of the circulation share in a house of 270 square metres — barely three metres — is PLN 40,000–50,000.
This is not an argument for a house without corridors. A corridor buys privacy, and that is its function. It is an argument for working out how much of it you are buying.
Three hundred metres: the threshold that costs PLN 900 a metre
In Poland, building services for a detached house of up to three hundred square metres of usable area carry 8 per cent VAT. Above that threshold the 8 per cent rate applies proportionally and the remainder is settled at 23. In practice every metre over the threshold costs about nine hundred złoty in tax alone.
An estimate at a build cost of PLN 6,000 net per metre, close to a shell standard. For a premium house the cost is higher, so this is a lower bound. There is no single method of calculating usable area for VAT purposes, and a garage inside the envelope is sometimes counted as part of it.
We check the VAT threshold at concept stage, including how the garage is counted. At that point moving two walls still costs nothing.
The same rate lets other decisions be costed. One parking space in a garage, about twenty-one square metres, is about PLN 125,000 of construction. A four-car garage in the 456-metre house costs about five hundred and twenty thousand — almost as much as the whole living zone of that house. A storey four metres high instead of three and a half means seventeen per cent more external wall and more volume to heat.
A garage costs as much as a living room
At twenty point seven square metres per space, our own median from the part on massing, one garage space is about PLN 125,000 to build. Not the finishes, not with the door or a resin floor — just the floor area.
The same house, the same rate per square metre. The garage taken from the schedule; the living area as living room, dining room and kitchen together.
This is not an argument against garages — for us the car is part of the brief, and we write about it separately. It is an argument for settling the number of spaces at the start and deliberately, because the fourth car costs as much to build as a quarter of the living room.
Height works the same way. A four-metre storey instead of three and a half means about seventeen per cent more external wall, volume to heat and height of stairs. That is the price of doors to the ceiling and floor-to-ceiling glazing, something we have done deliberately since 2024. It is just worth knowing that you pay for it, and then pay again every winter.
What this model cannot withstand
Every life-cycle cost model rests on assumptions, and it is only honest to show how much the result depends on them. We worked it out.
| If the assumption changes | The result changes by |
|---|---|
| Construction cost a thousand złoty per square metre higher or lower | 7–9%, together with repairs calculated from the construction value |
| Repairs and maintenance at two per cent of the value a year instead of one | 13–16% upwards |
| Cleaning rate: PLN 70 instead of 110 an hour | the whole item falls by a third, and it is the second cost of a house after construction |
Model calculated at 2026 prices, without inflation and without the plot. Assumed: construction PLN 8,000 per square metre, repairs 1% of the value a year, weekly cleaning at PLN 110 an hour.
One thing follows from this that is worth remembering when reading all the figures in this part: the absolute values are indicative, while the proportions between the items are robust. With any reasonable set of assumptions construction stays at about half the bill, cleaning is second, repairs third, and energy closes the list with a few per cent. That is a result no change of rate can reverse.
Energy: four per cent of the bill, in five months
Energy is the item talked about most and the one that weighs least in a thirty-year bill: 3 to 4 per cent. For the houses in the base it comes to between PLN 3,400 and 15,400 a year, depending on size.
The distribution across the year is more interesting. For a house of 268 m² the model gives from about 94 kWh in July to 735 kWh in January, that is from PLN 106 to 830 a month. About 70 per cent of the annual bill falls in the five months from November to March.
kWh per month
Model: 20 kWh/m² a year, of which 75% is heating distributed by degree days and 25% hot water and ventilation distributed evenly.
The roof as a water source
The average resident of Poland uses about 92 litres of mains water a day. A good part of that goes on flushing the lavatory and on laundry, that is on uses which do not require drinking water. Manufacturers of rainwater systems assume about 21 m³ per person a year for those.
With annual rainfall in the Łódź region of around 580 mm, the roofs of our houses collect between 41 and 222 m³ of rainwater a year.
A runoff coefficient of 0.8 is assumed and a roof area equal to 1.1 times the ground-floor area. In ten of the twenty units, rainwater would cover the whole annual use for the lavatory and the washing machine.
An annual total is not the same as real coverage, though, because rainfall is unevenly distributed: most in July, least in February. How much can actually be used is decided by the size of the tank. The 10 m³ tank we designed in one of the houses corresponds to roughly five weeks of demand for a family of five.
A year in the life of a house, month by month
The electricity bill and the rainwater off the roof run in exactly opposite directions through the year. Which is why they are worth seeing on one calendar, not only as annual totals.
Rainwater
Rainfall of 580 mm a year, distributed from a minimum in February to a maximum in summer. A family uses about 11 m³ of water a month, of which roughly a third goes to the lavatory and the washing machine.
In summer the roof collects ten cubic metres a month and covers the whole use for the lavatory and the washing machine. In winter it collects three and covers half. Electricity does the opposite over the same period: most in January and February, least in July. The tank is therefore there to move the surplus from July to September, not to close the annual balance.
And one more thing that only shows up on a calendar: for seven months, from October to April, bedroom windows are closed at night. That is the same period in which, without mechanical ventilation, carbon dioxide passes two thousand ppm — which we describe in the part about air.
Embodied carbon: a cost that is not in złoty
European baseline values for residential buildings speak of four hundred to eight hundred kilograms of carbon dioxide per square metre over a full life cycle. A Spanish analysis of a detached house gave three hundred and eighty-five kilograms per metre for the construction phase alone.
An estimate from baseline values per square metre, not a measurement of these houses. The footprint rises linearly with area: every 100 m² is about 40–80 tonnes.
Forty to eighty tonnes for every hundred square metres is a number that behaves exactly like cost: it rises with floor area and does not depend on what those metres are. A corridor weighs as much as a living room.
What this model does not cover
We say this outright, because a life-cycle cost model is very easily presented as a measurement, when it is a calculation on adopted rates.
- There is no plot, no fittings, no garden, no insurance and no property tax.
- There is no inflation and no cost of money over time. All amounts are in 2026 prices.
- The cleaning rate weighs very heavily. At PLN 70 an hour instead of 110 the whole item shrinks by a third.
- Every PLN 1,000 of difference in the build cost per metre changes the result by 7–9 per cent, because repairs are calculated as a percentage of build value.
- Taking repairs at 2 per cent a year instead of 1 adds 13–16 per cent to the total.
- Twenty units from one practice are not a representative sample of Polish house-building, and we never treat them as one.
What follows from this in design
Three rules that follow from it.
First, we count circulation during the concept, not after it. The share of circulation in the floor area is one of the numbers we give the client along with the first plan, next to the area and the volume.
Second, we hold the conversation about square metres by type of space. A metre of terrace and a metre of living room are two different financial decisions.
Third, we treat cleaning as a design parameter. The number of surfaces to be washed, how reachable they are, the kind of finish, and whether the equipment has somewhere to stand, are decisions worth more over thirty years than the entire heating installation.
Sources. Build costs 2026: Ongeo, Murator, Freenance. The rule of 1–4% of value a year for maintenance: University of Minnesota Extension, Metrobank, Nasdaq. G11 electricity price from January 2026: Murator. Water use of 92 l per person a day: Statistics Poland via Rankomat. Non-potable water demand of 21 m³ per person a year: Wilo. Rainfall in the Łódź region 1966–2021: University of Łódź and IMGW. House data: MOOMOO detached house plan study, final edition, October 2026, parts 17 and 18.
Licence. The figures and charts in this part are released under CC BY 4.0. They may be quoted, adapted and used commercially, crediting MOOMOO Architects as the source. Photographs and visualisations are not covered by the licence.
The whole study in one file
A hundred and thirty-five pages, twenty houses and apartments, fourteen parts and a hundred and eighteen drawings. Everything this series was built from, in full. The file is in Polish; the drawings and tables read without it, and an English edition is in preparation.
135pages 20houses 14parts 118drawings
Prefer to look first? The whole series is readable here, part by part, without signing up.
Compiled by: Łukasz Pastuszkaarchitect, co-founder, MOOMOO Architects